New Data Centre (Zurich)

New Data Centre – Full Design and Installation

Client:

Investment Bank (Zurich)

Industry:

Financial Services

Client Requirements

Cabling for a new data centre. 

Contact us for a free quotation:

Remarkable Aspects

The whole installation was completed within 10 working days.

Resolution

Working in Switzerland’s largest city, the Bluepoint Technologies team took on this project to cable a new data centre for an investment bank. 

The installation entailed the fitting of 2,800 fibre LC terminations and 4,800 Cat6 copper cross connects, between the core switches and server racks. Also included in this project was the design and installation of the LAN backbone links. The whole installation was completed within 10 working days as required.